How much concrete does one fence post take?
Work out the volume of the hole as a cylinder, then take out the space the post fills. Hole volume is π × radius² × depth, with everything in feet. Post volume is width × width × depth for a square post.
Use the actual size of the lumber, not the name. A 4x4 measures 3.5 by 3.5 inches and a 6x6 measures 5.5 by 5.5 inches. For a 4x4 in a 12-inch hole with 24 inches of concrete: π × 0.5² × 2 = 1.571 cu ft, minus 0.292 × 0.292 × 2 = 0.170 cu ft for the post, leaves 1.40 cu ft. Divide by the yield printed on the bag to get bags.
Bags of concrete per fence post chart
Depth here is the depth of concrete, not the whole hole. If you put 6 inches of gravel in the bottom, subtract it first. Bag counts use the yields Quikrete publishes: 0.375 cu ft for a 50 lb bag of Fast-Setting Concrete Mix, 0.45 cu ft for 60 lb and 0.60 cu ft for 80 lb Concrete Mix. Counts are per post and not rounded, so add up the whole job before rounding.
| Post and hole | Concrete depth | Concrete per post, cu ft | 50 lb fast-setting bags | 60 lb bags | 80 lb bags |
|---|---|---|---|---|---|
| 4x4 in 10 in hole | 18 in | 0.69 | 1.8 | 1.5 | 1.2 |
| 4x4 in 10 in hole | 24 in | 0.92 | 2.5 | 2.0 | 1.5 |
| 4x4 in 10 in hole | 30 in | 1.15 | 3.1 | 2.6 | 1.9 |
| 4x4 in 12 in hole | 18 in | 1.05 | 2.8 | 2.3 | 1.8 |
| 4x4 in 12 in hole | 24 in | 1.40 | 3.7 | 3.1 | 2.3 |
| 4x4 in 12 in hole | 30 in | 1.75 | 4.7 | 3.9 | 2.9 |
| 4x4 in 12 in hole | 36 in | 2.10 | 5.6 | 4.7 | 3.5 |
| 6x6 in 16 in hole | 24 in | 2.37 | 6.3 | 5.3 | 4.0 |
| 6x6 in 16 in hole | 30 in | 2.97 | 7.9 | 6.6 | 4.9 |
| 6x6 in 16 in hole | 36 in | 3.56 | 9.5 | 7.9 | 5.9 |
| 6x6 in 18 in hole | 24 in | 3.11 | 8.3 | 6.9 | 5.2 |
| 6x6 in 18 in hole | 30 in | 3.89 | 10.4 | 8.7 | 6.5 |
| 6x6 in 18 in hole | 36 in | 4.67 | 12.5 | 10.4 | 7.8 |
How big and deep should a fence post hole be?
Quikrete’s post-setting instructions call for a hole about three times the width of the post, which is roughly 10 to 12 inches for a 4x4 and 16 to 18 inches for a 6x6. The hole diameter is what drives the bag count: going from a 10-inch to a 12-inch hole on a 4x4 adds about half again as much concrete.
For depth, Quikrete gives one-third of the overall post length, plus 6 inches for a gravel base. An 8-foot post set for a 6-foot fence would sit in a hole about 32 inches deep before the gravel, so plan on digging about 38 inches and filling about 32 inches of it with concrete. Where the post carries a structure such as a deck, Quikrete says to go at least 6 inches below the frost line. Your local code or HOA may set its own minimums, so check before you dig.
Fast-setting mix or regular concrete mix?
Fast-setting mix is made for posts. You pour it dry into the hole around the braced post and add water, and Quikrete lists a set time of 20 to 40 minutes. It yields less per bag, 0.375 cu ft for 50 lb, so you buy more bags for the same hole.
Regular 60 or 80 lb concrete mix is mixed in a wheelbarrow or mixer first and takes longer to set, so the post has to stay braced longer. It gives more concrete per pound and is the cheaper route when you are setting a long run of posts and have help mixing.
Worked example: 14 posts for a 4x4 privacy fence
Holes are 12 inches across and 30 inches deep, with 6 inches of gravel in the bottom, so each hole gets 24 inches of concrete. Per post: 1.571 − 0.170 = 1.40 cu ft. For 14 posts: 1.40 × 14 = 19.61 cu ft.
The fence post concrete calculator adds 10 percent extra by default for uneven holes: 19.61 × 1.10 = 21.57 cu ft. That is 21.57 ÷ 0.45 = 47.9, so 48 bags of 60 lb mix, or 21.57 ÷ 0.375 = 57.5, so 58 bags of 50 lb fast-setting mix, or 21.57 ÷ 0.60 = 36.0, so 36 bags of 80 lb mix. Without the extra, the 60 lb count would be 44 bags.
The gravel base is separate: π × 0.5² × 0.5 = 0.39 cu ft per hole, or 5.5 cu ft for all 14, about 0.2 cubic yards.
Before you buy and dig
A few things change the count more than people expect.
- Dig one hole first and measure it. Augers and post-hole diggers often cut wider at the top than the bit size.
- Ending the concrete a couple of inches below grade and crowning it, or backfilling with soil, reduces the concrete per post.
- Round once for the job, not per post. Rounding each post up to whole bags would buy 56 bags of 60 lb mix in the example above, against 48 for the whole job even with 10 percent extra.
- Call 811 a few days before digging so buried utility lines are marked.
Using the fence post concrete calculator
Enter the number of posts, the hole diameter, the concrete depth (hole depth minus any gravel) and the actual post width: 3.5 for a 4x4 or 5.5 for a 6x6. Then set the yield per bag to match what you are buying, such as 0.375 for 50 lb fast-setting or 0.60 for 80 lb. The calculator subtracts the post, adds your extra percentage and rounds the bag count and mixer batches up.
For footings, slabs or a pier that is not around a post, the concrete bag calculator converts any volume to 40, 60 or 80 lb bags. For posts, rails and pickets on the whole fence, use the fence material calculator.
Sources and further verification
Bag yields and post-hole sizing come from Quikrete’s published product data and project instructions. Check the yield printed on the exact bag you buy, since products and sizes vary.