Calculation Methodology

Every calculator follows the same order: measure, convert units, adjust for the material, convert to packages or loads, then round up what you buy. A 20 × 12 ft slab at 4 in shows it: 80 cu ft, then 2.96 cubic yards, then 3.26 with 10% extra, then 147 bags of 80 lb.

Open the calculator for this job

1. Measure first, assume later

Dimensions give area, volume or length through fixed formulas, and odd shapes get split into simple measured pieces. The engine keeps more decimals than it shows, so on-screen rounding never stacks up in later steps.

The fixed conversions are 27 cubic feet per cubic yard, 2,000 lb per ton and about 0.7646 cubic meters per cubic yard.

2. Adjust only where the material needs it

Waste is not compaction, and neither is settlement. Each one appears as its own editable input, and only on the calculators where it applies. Density turns volume into weight without changing the volume. Package yield turns volume or area into whole bags, boxes or rolls.

3. Keep what you need apart from what you buy

Continuous amounts like cubic yards keep their decimals. Anything sold as a whole unit (bags, boxes, pallets, truck trips) rounds up, because you can’t buy part of one. When you enter a price per package, cost uses the rounded purchase quantity.

4. Replace the defaults with your numbers

Defaults are starting points. Coverage, density, payload, design depth and local rules should come from your supplier, the manufacturer, the project documents or a qualified professional whenever you have them.

Sources and further verification

These are the references behind the numbers above. If your supplier or the bag label gives a different figure for your exact product, use theirs.

Planning boundary

Check your measurements, the product data and the supplier’s selling unit before you buy. For anything structural or safety-related, get a qualified local professional involved.