Fence Material Calculator

A 100 ft picket fence with posts every 8 ft and one gate needs 15 posts, 39 rails and 230 pickets. Setting those posts in 12 in holes 30 in deep takes 62 bags of 60 lb concrete, with 10% extra on the pickets and the concrete.

Best for: a complete picket fence run, gate posts and post concrete included.

Your project measurements

ft
ft
in
in
Edit assumptions & pricing
in
in
in
cu ft
%
100 ft fence run 8 ft spacing
    Live measurement plan. Schematic, not to scale; values update as you edit.
    Estimated total — Enter project measurements to calculate.

    How the Fence Material Calculator works

    The run is split into sections at your post spacing, rounded up. You get one post per section plus the end post, and each gate adds one, the way Lowe’s fence planning worksheet counts them. Rails are sections times rails per section, and pickets fill the full run at picket width plus gap.

    Post spacing changes the order most. Tighten the default 8 ft to 6 ft and the same run needs 19 posts instead of 15, and 79 bags of concrete instead of 62.

    This page starts from 8 published figures and 3 planning values, each listed under Sources and verification below. When the bag, the box or your supplier’s quote says something different, type their number under “Edit assumptions & pricing” and the plan updates.

    Formula

    1. Sections = fence run ÷ post spacing, rounded up
    2. Posts = sections + end posts + gate posts
    3. Pickets = usable run ÷ (picket width + gap)
    4. Concrete = cylinder hole volume − post volume, multiplied by posts

    Worked example

    The default fence: 100 ft long, posts 8 ft apart, 3 rails per section, 5.5 in pickets with a 0.25 in gap, one gate, and 4 in posts in 12 in holes 30 in deep.

    1. Sections: 100 ft at 8 ft spacing rounds up to 13.
    2. Posts: 13 sections, plus 1 end post, plus 1 gate post = 15.
    3. Rails: 13 sections × 3 rails = 39.
    4. Pickets: the 100 ft run at 5.5 + 0.25 in per picket, plus 10%, rounds up to 230.
    5. Concrete: each hole minus its post, times 15 posts, plus 10%, comes to 62 bags at 0.45 cu ft per 60 lb bag.

    Your material plan reference

    The table fills in from whatever you entered above. Anything sold in whole units is already rounded up, while volumes and weights keep their full precision from step to step.

    Material or measurementCurrent calculated quantity
    Calculate to populate

    What usually goes wrong

    • Forgetting the gate posts. Each gate adds a post and a hole of concrete; with no gate this run needs 14 posts and 58 bags. A wide or heavy gate may need its own pair of stout posts, so add one by hand if yours does.
    • Rounding sections down. The short last section still needs a post at its end.
    • Copying a neighbor’s spacing. Wind exposure, fence height and local rules can set post spacing and depth, and this page doesn’t check either.
    • Buying fasteners straight off the estimate. The 1,380 here assumes two per picket per rail; your fastener schedule may differ.

    Frequently asked questions

    How many posts do I need for a 100 ft fence?

    At 8 ft spacing, 14 posts for a straight run, or 15 with one gate. At 6 ft spacing it’s 19 with the gate.

    How are pickets counted?

    The full run in inches is divided by picket width plus gap, then 10% is added and the total rounds up. With 5.5 in pickets and 0.25 in gaps over 100 ft, that’s 230.

    Does the concrete include the gate posts?

    Yes. Every post on the list gets a hole of concrete, gate posts included.

    Sources and verification

    Check post spacing and hole depth against your local code and the fence maker’s instructions. Then replace the 0.45 cu ft bag yield with the number printed on the bag you buy.

    Where the defaults come from

    No published figure backs these, so treat them as planning values and set them for your job: gap between pickets, post width, fasteners. Prices are placeholders; use your supplier’s quote.

    The geometry and unit conversions behind this page are written out in the calculation methodology. The sources and verification policy says where the defaults come from and what they don’t claim.